K. Banphot,
PO was issued yesterday.
Why just issued PO?
Project has been delayed. We were supposed to mass production for those models in February but I was informed mid January 2016 that still no samples. We took another 1 month to issue PO for samples. How serious we are? What is final schedule for this project?
Thanks
Chatree
Dear K.Chatree
I just got the PO on hand in this morning and sorry for long lead time for issue the PO.
And schedule for this project I make the action plan in the attached.
If samples are arrive to factory on W1 Mar Target MP on W3 Jun’16 .
Best regards,
Banphot P.