Dear Khun Uthai, Khun Prakasit and Khun Montree
Please be informed all issue about scaffolding.
1.Next process after AML are SQ number request and JDE add new supplier that will take time 5-7 days. Which finance already evaluated financial statement.
2.Lead time most items within 60 days that shorter than previous order.
3.Lower Price, for pipe cap and bolt cap lower than present JDE price ( 55 THB/ea. for pipe cap and 35 THB/ea. for bolt cap) also for alternative are local made 25 THB/Ea. and 10 THB/ea. respectively. Which sample will deliver to BKKHA end of Apr.
4.Ladder / DBI-SALA are not main products of Thai Const but Supplier can supply Krub.