As discussed and agreed during the meeting on 3 Feb 2016, please find attached file for our Catch up plan of structure works for your review and comments.
I would like to explain you briefly that I had a meeting with another RC works contractor(CMC) on 4 Feb then CMC confirmed to us that they can mobilize around 200 workers (Myanmar & Cambodian) by middle of Feburary.
Now, the work permit process for workers moving to Korat area is under proceeding and it can be finished by 18 Feb.2016.
CMC will take over UT2 & Canteen area then SKC will concentrate for Main building area only.
As per my review for the catch up schedule, UT2 area is critical path now and CMC will mobilize foreign labours for this area then it will be helpful for working during the Songkran holiday(09 Apr ~ 17 Apr) also.
I will discuss with you more detailedly for our catch up plan when I go back to site from my vacation on 16 Feb.
And also, we will submit the catch up plan for overall works by 25 Feb 2016 as agreed.
Thank you for your kind attention and support always.