Machines Unpacking & Positioning for TST
A: Preparation for the operation,
1) Upon receiving the packing list from TST, we must check :
The volume of containers and machines
Dimension and weight (N/W & G/W) of the machines
2) From the details of the packing list, we can prepare equipment such as forklift, crane etc. That suitable for the machines. Make sure that the staff who operate the equipment must have certificate. The number of manpower must be enough for each operation.
3) Place check of operation floor (First or Second Floor)
4) All equipment (Crane, Fork Lift) must have certificate inspection and test from Inspector Engineer who have certificate from Welfare Department
5) All staff who to operation on that day must knowledge and join TST safety course first
6) Inspect the area:
Entrance, must be wide and tall enough for the machines to enter
Floor, must be strong enough to handle the weight of the machines. Some
floor may need to put plastic sheet, card board, or PVC sheet to protect
damaging.
Passage way, must be wide enough and no obstacle