Dear K Pairoaj
What you are doing now in public in the project group line is exactly what I tried to explain in our monthly meeting with MDE management last Wednesday.
We explained to you about the atmosphere in the project and the very negative usage of the line group being done by some of MDE people.
What you did today is exactly what I meant.
Let me remind you that building A was the last area to be handed over with 1 month delay and it's the most complicated area in the project.
Indeed our subcontractor workers left the site today at 17:00 to get their payment and go buy some food, it's reasonable since they are human and need to eat and feed their families, this people are working all month 7 days per week.
The element they were trying to prepare for casting today will be casted tomorrow together with Other elements that were planed for tomorrow.
Our site manager is doing a great job and we are all there to support him when ever he needs.
I personally talked to the Subcontractor but he explained to me the situation with the workers and there was nothing we could do about it.