CIVIL WORK NOTES:
1. Submission price have to include the permit operation (permit+ construction drawing + list …….)
The contractor have to prepared safety equipment including the safety method. (all equipment must be available for inspection)
2. Detail of works may be changed it later for suitable the venue.
3. The contractor have to specified the warranty period for consideration.
4. Work detailed is based document as the standard, if there is any doubt please Q&A before submit price.
5. Master plan will be made as scheduled, if delay have to be adjusted 1/1000 of the total amount / day and have an impact on the bidding next time.
ELECTRICAL WORK & MECHANICAL WORK:
1. Submission price have to include the permit operation.
2. The contractor have to specified the construction period along with quotation.
3. Work detailed is based document as the standard, if there is any doubt please Q&A before submit price.
4. Detail of works may be changed it later for suitable the venue.
5. The contractor have to prepared safety equipment including the safety method. (all equipment must be available for inspection)
6. If the contractor is delayed due to problems such as material shortages, labor or other circumstances, the contractor was warned by SCM supervisor and
If this does not work completed on schedule and affect to TMT, the contractor was adjusted 1/1000 of total amount / day and have an impact on the bidding next time.