We just got information from factory that they can’t add in wk.09 RSW. the best schedule as now is wk.11.
Seems now mat’l also tight as MDR-ZX310 in wk.09 is very high demand on this model .
And they limited with cap housing mold capacity as initial wk.09 now also very tight for them.
For the additional is difficult to pull in
Are you Ok for WK11?
If ok , pls reflect these POs by transmission this wk.