Question 1: What do you mean by a dummy activity? Why it is used in networking?
Question 2: Depict the following dependency relationships bymeans of network diagrams.(The Alphabets stands for activities)
1. A and B control F; B and C control G.
2. A and B control F; B controls G while C controls G and H.
3. A controls F and G; B controls G while C controls G and H.
4. A controls F and G; B and C control G with H depending upon C.
5. F and G are controlled by A, G and H are controlled by B with H controlled by B and C.
6. A controls F, G and H; B controls G and H with H controlled by C.
Question 3: Develop a network based on the following information;