Thank you for your time spent for our discussion this afternoon.
I’m writing here to summarize our discussion;
1. Airfreight for Hoist shipment - Cost ˞ 250,000 THB.
Deduction 50,000 THB. (Sea freight)
Add cost 200,000 THB.
- Time - 5 days faster can be expected by Airfreight.
This additional cost has to be discussed between Umemura and Valeo.
In our Tebodin opinion, this should be bared by Umemura as a cost of delay reduction.
2. Manufacturing time
- Shanghai factory still insisted on 25-Sep-2015.
- KONE Thai still keep on pushing Shanghai factory.
- Further updates will be ASAP giving by KONE Thai.
3. Shop works and Site installation
- In the view of KONE, there is a possibility to reduce by 2 days from an original plan of 7 days.
If those will be agreed, we’ll have a new shorter timeline as follow.
Current New
- Done of Girder assembly + End carriage, 20-Sep-2015 20-Sep-2015
- Hoist + Control devices arrival at KONE’s shop, 12-Oct-2015 07-Sep-2015
- Done the shop test, 15-Oct-2015 09-Sep-2015
- Done the site installation + Commissioning + Handover, 18-Oct-2015, 11-Sep-2015