I would like inform you about schedule crushing 16/17 rev.1 and load rejection.
Detail :
- 2/1/17 : Start crushing and export line 1.
- 9- 10 /1/17 : First Sync. EDC line 2 and test load rejection.
Noted : Shinko and CPT Check and fix all problem prepare for first Sync before start crushing.