We would like to update the latest status :=
Modification
Modify program to generate temporary password as per requested, completed, will be installed on Oct 30-31
Modify Web Self Service to add more option to accept “Location”, completed, will be installed on Oct 30-31
Modify program to Setup workflow in part of “Location”, completed, will be installed on Oct 30-31
Installation
Windows application and Web application for standard features has been installed
We will be installed the new modification for the final on Oct 30-31
What to do next,
Today Oct 24, Eagle team will review data in QA system to make sure that the modification program and the data are match and can run.
Today, Eagle team will call AAT HR Team to check the proper time to make a conference call, we would like review user in “Location” and make the same understand, which targeted in the afternoon.
Eagle team will do final setup regarding to the user in “Location” in QA system
From Oct 24 to 29, Eagle team will Test the new application which modified in details above in order to make it clean before install on Oct 30-31
Web Self Service UAT
Eagle team can do UAT for Web Self Service from Nov 3 and onward, HR Team please advise for the date.
Attached file is a schedule excel file, It is the same old one since Tuesday 21,
Thank you and Regards