Note that at 20% of work done (AreaDone), more than 70%
of all spools have been delivered to the site. According to
Howell and Ballard's rule of thumb, this is a favorable indicator
for project success. As will be shown later, it is no guarantee for
project success, however, particularly when out-of-sequence
work leads to mismatches.