a. KCC and Allied Metal go thought area by area to clarify Kitchen work from L35, L36, L37, L38 and L39 Note L33 not yet.
b. Kitchen work at PA coordinate with KCC for BOH by VPL except L37’s BOH with KCC.
c. KCC (K.Pim) with List Key issue to remind on each area for reference.
d. KCC (K.Pim) with develop check list to identify sequence of work: A). Kitchen has to be done first, B). ID has to be done first and C). All both do together.
e. Note: on Kitchen drawing if have Kitchen code number almost done by Allied Metal.