5.2.3 water supply
- evaluation of impacts on water supply of local people due to water demand for industry both during construction and operation of the industrial estate.
5.2.4 transportation/communication
- description of increased traffic volumes of the project expected in the future and their effect to existing condition
5.2.5 agriculture
- description of the existing agriculture in and surrounding the project area and estimation of value of land to be changed due to proposed industrial estate.
5.2.6 public risk/hazard
- evaluation of environment protection and management of public risk and hazard of the project during construction and operation in case of explosion, spills/leaks and operation failure.
5.3 third priority
5.3.1 general assessment of other environmental resource
- general evaluation on environmental effects of other environment resource on such aspects as soil (erosion/silt run off) , drainage/channel pattern, employment, aesthetics/visual quality, surface water hydrology , forest/plant community and housing.
6. recommended format for preparation of EIA
The process of reviewing and evaluating EIA submitted to ONEB will be greatly facilitated if standard format is used.
7. additional information