1) FHI agree and will be informing to TKS regarding additional 2K clear mixing equipment
2) Review master schedule of Paint Shop Building construction + TKS equipment installation
- Feedback from FHI, TKS request 2 months Equipment Installation + 2 months Commisioning
after building construction completed
- In this case, it will delay 3 months of equipment hand over, then delay SOP
- Suggest best time for commisioning before June 2018
- WEI team will consult SMCC and TKS for this new schedule and revert
- Need training to workers as well before handover equipment