Personal Planning Process(PSP1)
•PSP1 and PSP1.1 focus on personal project management techniques,
•introducing size and effort estimation, schedule planning and schedule tracking methods
•Size and effort estimates are made using PROBE (PROxy Based Estimating) method
•With PROBE engineers use the relative size of proxy to make their initial estimate
•PROBE is based on the idea that if an engineer is building a component similar to one he built previously, then it will take about the same effort as it did in the past.