Dear Ms Lalliya and team,
Regarding the captioned subject, we would like to inform you the next action for B&V Ratchaburi Scrap pieces.
MHPS requests to repair 83 pcs which became Acceptable by MHPS TA's remeasurement.
・Result of remeasurement
83 pcs of the scrap 104 pcs became Acceptable based on new criteria by
remeasurement of visiting inspection TA.
(for detail please see attached file.)
According to this result, we would like to revise MHPS answer for ISP
report and send them officially later.
(Embedded image moved to file: pic00491.gif)
・83pcs Acceptable blade (Repairable)
MHPS is hoping to use these repaired components to Ratchaburi next
turbine inspection(10/B).
Therefore,Could you let us know when EDS complete repair at earliest ?
(Order of priority: #1-1,#1-2 → #2-1,#2-2)
Please let us know your plan date for the following 4 item.
1. Plan Sending Repair Plan Report by sales force
2. Plan Finish date from operation
3. Plan Sending Final Report
4. Plan Cargo Ready
・21pcs Scrap(Unrepairable)
MHPS is considering how to treat scrap pieces.
As soon as next action is decided, we would like to let you know.