Dear Tomohisa san , Nishiyama san :
O HA YOO GO ZAI MA SU (Good morning !)
GO KI GEN I KA GA DE SU KA ( How are you ? )
Thanks for you below information.
We are please to inform to you that we will use The Tool running production first
and delivery the part to you as the below :
- PGUMS2592BSZZ
8/25 9/02 = 835pcs
- PGUMS2593BSZZ
8/25 = 100pcs
After that we will make continues to finish .
The schedule of Tool fabrication as the below :
8/27 to 9/03 = Continues make Tool
9/04 Texture , Polish Tool
9/05 Engineer Trial sample
9/08 Sample fully cavity to Nishihara san/SMTL.
PGUMS2592BSZZ 100csv.
PGUMS2593BSZZ 49cav.
Are you accept the above schedule ?
Please advise me