The delays have directly impacted on the design, procurement, fabrication and installation. The actual delay due to the disruption is impossible to exactly calculate because some panels were fabricated during the disruptive period at the original factory, however taking into account all of the above delaying events, a four months delay is considered to be a conservative estimate.