When the Central Embassy project commenced, the factory provided a production slot for the whole project. Because the project incurred substantial delays, the production slot had to be moved in order to accommodate the new project schedule. If the factory is not operating at full capacity, it can accommodate some of the changes, however if the factory is running at high capacity it cannot accommodate changes to the project schedule.