OWNER/ Consultant inform Contractor (CPP-ESP JV) that Contractor shall comply with following requirements for all tree cutting activities.
- for both Section 1 and Section 2 of the pipeline route, all tree cutting activities shall be in compliance with Department of Highway (DOH) and Department of Forestry requirements.
- for Section 2 of the pipeline route;
o A tree cutting plan shall be developed by Contractor and submitted to OWNER/ Consultant construction supervision teams at least two (2) weeks in advance before commencement of cutting activities. The plan should include;
Date of cutting;
Start and end kilometre posts (KP)
Species, and number and diameter/ perimeter of trees
Any concerns related to community
o All trees shall be marked and recorded before and after cutting. OWNER’s representative shall endorse all records. A copy of the records shall be submitted to OWNER/ Consultant for information.
o Tree cutting shall be conducted under Contractor’s Community Relation (CR) supervision