Dear Mr. Paiboon.
The Flat Pack Office Building is ready for handover from this morning. Missing flashing element has been site delivered yesterday and Installed this morning.
Regarding the Toilet: - embedded septic tank still need some corrections which need the use of an excavator. (2hours works and it is done)
- For the toilet commissioning Could you kindly provide Water and fill the water supply system tank installed on the top of the toilet container?
- Regarding the house keeping before handover: 1) could you please show us where construction waste are supposed to be dropped
2) could you also tell us where spare water tank we are in charge to supply should be put
3) The empty furniture Equipments’ Container will be shift back : we need a crane, Sling / Shekels for rental. Could you manage? The trailer is coming from Thailand and need to be inform at least 2 days in advance.
Thanks a lot for your support