Distribution transformer data analysis
The Bangalore electricity supply company (BESCOM.) has 1, 38,618 distribution transformers (BESCOM. Annual report 2010) covering supply for eight districts. The rating of the transformer depends upon the concentration of load at a given location and they range from 2 kVA. to1000 kVA.
A distribution transformer in a residential locality is taken for study in this article. The details of the transformer are as follows:
• Transformer: TC 86; location: South Bangalore.
• Rating: 250 kVA, 11 kV/415 V, 50 Hz, 3 phase, distribution trans- former.
• Total number of poles = 82.
• Total number of consumers = 386.
• Total connected load = 782 kW.
Data set gives details regarding category of consumer, pole from which he is served and connected load or sanctioned load of individual consumers. The diagram of the distribution transformer network shows connection from the transformer to the poles and pole to pole, type of conductor used and the distance in meters.
Power supplied through distribution transformer is collected once in 30 min, continuously using Electronic Tri-vector Meter (ETVM.). The ETVM. meter constant is 80. The readings are recorded over a period of one month at 30 min interval. The average value of the power corresponding to each time interval over the entire day (0:00–23:30 h) is calculated using the readings for 31 days down- loaded from the meter. The average daily variation of the load on the distribution transformer so obtained is used in this work. The plot of average variation of power with time of the day is shown in F4.
Peaking of the load curve is observed in the morning as well as in the evening hours. It is seen from the graph that maximum peaking takes place in the morning hours between 6.00 am and 8.30 am. One of the reasons for peaking during morning hours is the use of electricity for pumping water to an overhead tank in every domestic consumer premises.
5. Investigations on policy impact
The distribution transformer under study is in a residential local- ity. It is found that 216 domestic consumers are having a connected load of 2 kW and above. A large number of them are having 3 kW which is the typical connected load of one house hold. The domestic consumers, with 2 kW and more connected load, have a motor- pump to fill their overhead tanks. It is a common practice in the city that water-pumps are switched on in the morning hours. This coincides with the peaking on the transformer. These motor pumps for use in houses, are generally 0.37 kW and are operated for about an hour or less. These 0.37 kW motor pumps are commonly used for a vertical lift of 15 m. The following investigations are carried out by replacing the 0.37 kW AC motor pumps by solar DC pumps.
5.1. Impact on peak shaving it is observed from the graph in Fig. 4 that maximum peaking takes place in morning hours between 6.00 am and 8.30 am. With the use of solar water pumps, motor load for pumping water gets eliminated from the grid supply.
It is estimated that out of 216 domestic consumers, if 150 (70%) of them operate their pumps from PV panels, a net reduction of 55.5 kW of total connected load on the transformer is observed. Similarly, if the remaining 66 (30%) pumps, which are generally switched on at night between 7.30 pm and 10 pm, also employ solar water pumps, a further reduction of 24.42 kW in connected load is observed. The resulting load on the distribution transformer during peak load hours is shown in Table 3.
Plot of power in kW and time in hours (0:30–23:30 h) is shown in Fig. 5. Peak load reduction with solar pumps in operation is observed from the graph.
5.2. Impact on line losses
The network of load on the secondary side of the local distribution transformer is very complicated with many poles spread in many streets and inter-connected with other poles. The consumer load is connected to the nearest pole via service mains. The distribution transformer diagram of T-86 is shown in Fig. 6 (service mains not shown). It is a single line diagram showing electrical connection between poles, distance and total connected load on each pole. In this secondary distribution network, three different types of conductors namely rabbit, squirrel and weasel are used. The resistance and reactance of these conductors per kilo meter length of the wire are listed in Table4.
…………………………………………………………………………………………………………………………………………………………….
Distribution transformer data analysis
The Bangalore electricity supply company (BESCOM.) has 1, 38,618 distribution transformers (BESCOM. Annual report 2010) covering supply for eight districts. The rating of the transformer depends upon the concentration of load at a given location and they range from 2 kVA. to1000 kVA.
A distribution transformer in a residential locality is taken for study in this article. The details of the transformer are as follows:
• Transformer: TC 86; location: South Bangalore.
• Rating: 250 kVA, 11 kV/415 V, 50 Hz, 3 phase, distribution trans- former.
• Total number of poles = 82.
• Total number of consumers = 386.
• Total connected load = 782 kW.
Data set gives details regarding category of consumer, pole from which he is served and connected load or sanctioned load of individual consumers. The diagram of the distribution transformer network shows connection from the transformer to the poles and pole to pole, type of conductor used and the distance in meters.
Power supplied through distribution transformer is collected once in 30 min, continuously using Electronic Tri-vector Meter (ETVM.). The ETVM. meter constant is 80. The readings are recorded over a period of one month at 30 min interval. The average value of the power corresponding to each time interval over the entire day (0:00–23:30 h) is calculated using the readings for 31 days down- loaded from the meter. The average daily variation of the load on the distribution transformer so obtained is used in this work. The plot of average variation of power with time of the day is shown in F4.
Peaking of the load curve is observed in the morning as well as in the evening hours. It is seen from the graph that maximum peaking takes place in the morning hours between 6.00 am and 8.30 am. One of the reasons for peaking during morning hours is the use of electricity for pumping water to an overhead tank in every domestic consumer premises.
5. Investigations on policy impact
The distribution transformer under study is in a residential local- ity. It is found that 216 domestic consumers are having a connected load of 2 kW and above. A large number of them are having 3 kW which is the typical connected load of one house hold. The domestic consumers, with 2 kW and more connected load, have a motor- pump to fill their overhead tanks. It is a common practice in the city that water-pumps are switched on in the morning hours. This coincides with the peaking on the transformer. These motor pumps for use in houses, are generally 0.37 kW and are operated for about an hour or less. These 0.37 kW motor pumps are commonly used for a vertical lift of 15 m. The following investigations are carried out by replacing the 0.37 kW AC motor pumps by solar DC pumps.
5.1. Impact on peak shaving it is observed from the graph in Fig. 4 that maximum peaking takes place in morning hours between 6.00 am and 8.30 am. With the use of solar water pumps, motor load for pumping water gets eliminated from the grid supply.
It is estimated that out of 216 domestic consumers, if 150 (70%) of them operate their pumps from PV panels, a net reduction of 55.5 kW of total connected load on the transformer is observed. Similarly, if the remaining 66 (30%) pumps, which are generally switched on at night between 7.30 pm and 10 pm, also employ solar water pumps, a further reduction of 24.42 kW in connected load is observed. The resulting load on the distribution transformer during peak load hours is shown in Table 3.
Plot of power in kW and time in hours (0:30–23:30 h) is shown in Fig. 5. Peak load reduction with solar pumps in operation is observed from the graph.
5.2. Impact on line losses
The network of load on the secondary side of the local distribution transformer is very complicated with many poles spread in many streets and inter-connected with other poles. The consumer load is connected to the nearest pole via service mains. The distribution transformer diagram of T-86 is shown in Fig. 6 (service mains not shown). It is a single line diagram showing electrical connection between poles, distance and total connected load on each pole. In this secondary distribution network, three different types of conductors namely rabbit, squirrel and weasel are used. The resistance and reactance of these conductors per kilo meter length of the wire are listed in Table4.
…………………………………………………………………………………………………………………………………………………………….
การแปล กรุณารอสักครู่..

หม้อแปลงการวิเคราะห์ข้อมูล
บังกาลอร์บริษัทประปาไฟฟ้า ( bescom ) ได้ 1 , 38618 จำหน่ายหม้อแปลงไฟฟ้า ( bescom . รายงานประจำปี 2553 ) ครอบคลุมจัดหามา 8 เขต การจัดอันดับหม้อแปลงขึ้นอยู่กับความเข้มข้นของโหลดที่ให้สถานที่และพวกเขาช่วงจาก 2 KVA . to1000 KVA .
จำหน่ายหม้อแปลงไฟฟ้าในสถานที่ที่อยู่อาศัยจะได้รับการศึกษาในบทความนี้ รายละเอียดของหม้อแปลงมีดังนี้ :
- หม้อแปลง : TC 86 ; ที่ตั้ง : ทางใต้ของอินเดีย การจัดอันดับ
- 250 KVA , 11 KV / 415 V , 50 Hz , 3 เฟส , การกระจายทรานส์ - อดีต
- รวมจำนวนของเสา = 82 .
- จำนวนของผู้บริโภค = 386 .
รวม 782 - โหลดเพลง = kW .
ตั้งค่าให้ข้อมูลรายละเอียดเกี่ยวกับประเภทของผู้บริโภค เสาที่เขาให้บริการและเชื่อมต่อโหลด หรือ โหลด ของผู้บริโภคและตามแต่ละบุคคล แผนภาพของหม้อแปลงจำหน่ายแสดงการเชื่อมต่อเครือข่ายจากหม้อแปลงที่เสาเสาเสาและชนิดของตัวนำที่ใช้ และระยะทางในเมตร
พลังส่งผ่านหม้อแปลงเก็บครั้งเดียวใน 30 นาทีอย่างต่อเนื่องโดยใช้เวกเตอร์ ตรีอิเล็กทรอนิกส์เมตร ( etvm . ) การ etvm . คงวัด 80 การอ่านบันทึกในช่วงหนึ่งเดือนที่ 30 นาที ช่วง ค่าเฉลี่ยของค่าพลังงานที่สอดคล้องกับแต่ละช่วงเวลามาทั้งวัน ( 4 ทุ่ม– 23 : 30 ชั่วโมง ) คำนวณโดยใช้ค่าวันที่ 31 ลงโหลดจากมิเตอร์วันเฉลี่ยผันแปรของโหลดหม้อแปลงจึงได้รับใช้ในงานนี้ พล็อตของการเปลี่ยนแปลงโดยเฉลี่ยของพลังงานกับเวลาของวันที่จะแสดงใน F4
จุดของเส้นโค้งโหลดเป็นที่สังเกตในตอนเช้าเช่นเดียวกับในเวลาเย็น จะเห็นได้จากกราฟที่จุดสูงสุดจะเกิดขึ้นในช่วงเช้าชั่วโมง ระหว่าง 6.00 น. และ 8.30 น.หนึ่งในเหตุผลสำหรับจุดในเวลาเช้า คือ การใช้ไฟฟ้าในการสูบน้ำในถังค่าใช้จ่ายทุกผู้บริโภคในประเทศนี้
5 ตรวจสอบผลกระทบของนโยบาย
หม้อแปลงภายใต้การศึกษาในที่อยู่อาศัยท้องถิ่น - ity . พบว่า มีผู้บริโภคภายในประเทศมีโหลดเพลง 2 กิโลวัตต์ขึ้นไปเป็นจำนวนมากของพวกเขามี 3 kW ซึ่งปกติโหลดเพลงหนึ่งครัวเรือน ผู้บริโภคในประเทศ , 2 กิโลวัตต์ และเชื่อมต่อเพิ่มเติมโหลด มีมอเตอร์ - ปั๊มจึงจะถังค่าใช้จ่ายของพวกเขา มันเป็นปฏิบัติทั่วไปในเมืองว่า เครื่องสูบน้ำจะเปิดในช่วงเช้าชั่วโมง นี้เกิดขึ้นพร้อมกับแนะนำในหม้อแปลง มอเตอร์ปั๊มเหล่านี้เพื่อใช้ในบ้าน , ทั่วไป 037 กิโลวัตต์ และจะดำเนินการประมาณหนึ่งชั่วโมงหรือน้อยกว่า เหล่านี้ 0.37 kW มอเตอร์ปั๊มปกติใช้ลิฟท์แนวตั้ง 15 เมตร ตรวจสอบต่อไปนี้จะดำเนินการโดยแทนที่ 0.37 kW DC AC มอเตอร์ปั๊มโดยปั๊มพลังงานแสงอาทิตย์
5.1 ผลกระทบบนยอดเขาโกนหนวดมันสังเกตได้จากกราฟในรูปที่ 4 ที่จุดสูงสุดจะเกิดขึ้นในชั่วโมงเช้า ระหว่าง 6.00 น. และ 8.30 น.ด้วยการใช้เครื่องสูบน้ำ มอเตอร์ โหลด เพื่อปั๊มน้ำได้รับตัดออกจากตารางอุปทาน
มันคือประมาณว่ามีผู้บริโภคภายในประเทศ ถ้า 150 ( 70% ) พวกเขาใช้ปั๊มของพวกเขาจากแผงเซลล์แสงอาทิตย์ การลดลงสุทธิของลูกค้าโดยรวมโหลดเพลงบนหม้อแปลงเป็นที่สังเกต ในทำนองเดียวกันถ้า 66 ( 30% ) ปั๊ม ซึ่งโดยทั่วไปจะเปิดตอนกลางคืนระหว่าง 730 น. ถึง 10 น. ยังใช้เครื่องสูบน้ำพลังงานแสงอาทิตย์ , การลดของ 24.42 กิโลวัตต์ในโหลดเพลงเป็นที่สังเกต ผลโหลดหม้อแปลงจ่ายโหลดสูงสุดในระหว่างชั่วโมงแสดงดังตารางที่ 3
พล็อตของพลังงานและเวลาในชั่วโมงกิโลวัตต์ ( 0:30 – 23 : 30 ชั่วโมง ) จะแสดงในรูปที่ 5 พลังงานแสงอาทิตย์ปั๊มยอดลดภาระในการดำเนินงาน คือ สังเกตได้จากกราฟ
5.2 . ผลกระทบต่อการสูญเสีย
เส้นเครือข่ายของโหลดในด้านทุติยภูมิของหม้อแปลงจำหน่ายในท้องถิ่นจะซับซ้อนมาก มีหลายเสากระจายในถนนหลายสาย และอินเตอร์ ที่เชื่อมต่อกับเสาอื่น ๆ ภาระผู้บริโภคเชื่อมต่อกับเสาที่ใกล้ที่สุดผ่านไฟบริการ หม้อแปลงไฟฟ้าจำหน่ายแผนภาพของ t-86 จะแสดงในรูปที่ 6 ( ไฟบริการไม่แสดง )มันเป็นบรรทัดเดียวแผนภาพแสดงการเชื่อมต่อระหว่างเสาไฟฟ้าระยะทางและรวมโหลดเพลงในแต่ละเสา ในมัธยมศึกษา เครือข่ายการกระจาย สามประเภทที่แตกต่างกันของตัวนำ คือ กระต่าย กระรอก และหนีไปใช้ และความต้านทานต่อเหล่านี้เป็นตัวต่อกิโลเมตร ความยาวของลวดอยู่ใน
table4 ...................................................................................................................................................................................
การแปล กรุณารอสักครู่..
