For method arrange shipment
• Engineer confirm which package number will be finished in advance (not confirm each item in the package ready)
• I advised you and Alisa, please contact direct to engineer , Can to do or not?
• Alisa san confirmed please arrange shipment on 29-30/July
• For UPCC & ALINCO, I think all people to know the customer request all item
• After container gone, our logistic will request original packing list in factory to Engineer
For double check item by item and report to Thai customer and approve detail on BL