All the necessary insulation jacket material was ordered as soon as we realized that the insulation was missed. However the long lead item is the insulation Jacket Dished End. Therefore the best ship date for the complete reactor will be week 11. This is assuming no 3rd party inspection is required.
Please note on 18 Dec I sent, upon your request, the revised ITP for the second reactor. If you wish to carry out inspections then please mark up any inspection points and return to us as soon as possible.