• Propulsion pump sump covers to be installed
• Grating for submersible pump pit to be installed
• Railing to be installed around pump pit
• Access ladder or stairs should be installed at the pump pit
• Open pipe penetration through the wall should be closed
• Concrete around HDPE pipe penetration near the wave pool to be closed
• Drain pipe in middle of pump room to be cut level to the floor and drain cover installed to stop large debris from going inside the pipe.
• Floors should slope to the drain
• Concrete should be installed at the filtration room entrance
• Plant room and filter room to be cleaned prior to handover to the client
• Equipment should be cleaned prior to handover to the client
• Mechanical room entrance door to close and lock