This work shall consist of furnishing all materials, equipment and labor necessary
for conducting an Osterberg Cell (O-Cell) Load Test and reporting the results. The
Contractor shall supply all material and labor as hereinafter specified and including prior
to, during and after the load test. The test shaft shall be constructed at the location shown
on the site plan and in accordance with the requirements of these special provisions and
also as outlined elsewhere in project plans and/or contract documents