Guest room B1-B4
- ND will be install dry wall which is additional work and to push finish
by the end of July 15
-ND to push for mock up guest room by next month to be finish.
- JWSto speed up for façade at the front roof all building to be finish
the end of 15 July 2016
- Ajanmmongkol to start for sample plant grass, trees, shrub out side
at Mock up
Main lobby
- JWSto finish pre -function roof by end of month & handover to MEP
and ND.
- JWSto install the steel support for ALTECH for all façade structure
and to speed up work.
- JWS modified drill door and wall of the laundry room added.
-JWS / CGD -Staircase to be designed from Pre- function to New
Multipurpose meeting room , JWS will redesign & submit drawing for
approval.
- CGD additional water next to ramp in Lobby entrance and PMC sent
SI,and sketch drawing already.
-The Balcony for new Meeting room with toilet, pantry , CGD
will prepare layout before Tuesday meeting
-JWSto start demolish brick work make new wall for spa after getting
revised layout from CGD & then handover to MEP / ND
-Spa zone CGD to be discussed with operator for sign off on Tuesday
and CGD submit to al