Platong has the shutdown plan in end of Aug. pls. provide your team to do battery charger maintenance na krub.
PLCPP2 Shutdown
No Equipment Activities POBs Schedule
1 Battery Charger Online/Offline Preventive Maintenance and Discharge Test (PLCPP2) 4 POBs Onboard 29-Aug Back 07-Sep
28-Aug-14 Standby at NST.
29-Aug-14 Onboard Platong.
07-Sep-14 Back to NST.
Tools to be arrived at SKL by 26 Aug. and load out to Platong on 28 Aug. (Thursday).
Update team for me na krub.