Refer to below improvement of delivery time for JB.
Facts
• Cluogh/PBI give approval drawing and green light to start production dated on 22/10/13
• Factory/PES promised delivery time 12 working weeks after drawing approval which mean 31/1/14
Therefore below here Hawke able to improve delivery time from 17/1/14 to 2/1/14.
If Clough really need faster delivery time than promised date.
I think it’s fair enough to ask for Air freight charge pay by Clough.
By the way Factory not possible to meet delivery before Christmas as per customer demand.