For each of the seven TPM pillars, written plans have been developed, for
example the planned maintenance plan is:
. expand breakdown successes to the rest of the department;
. continue to support autonomous maintenance;
. expand the development of computerised systems;
. continue with stock reduction;
. expand zone maintenance systems to other machines;
. develop thermal imaging systems to incorporate mechanical parts;
. communicate with suppliers for other systems (e.g. vibration analysis);
. continue the development of systems for tighter budget control; and
. review maintenance costs.