All construction work must be completed according to the IISBV approved room specification.
All low voltage cabling (computer, telephone, CCTV, public address systems are installed within the ceiling grid and / or cable trays. Allow 10meters of additional cabling for flexibility when placing the Sales counters/Furniture test machines. Only the final connection to the appliance should be necessary.
All HVAC systems are installed and ready for final testing.
All plumbing and water and Air Conditioning works are completed.
Commercial lighting cabling is fully installed, commercial light fittings are placed as per the lighting plan and connected to the grid power supply
General lighting (TL 5 fluorescent) is installed and fully operational.
All high voltage and electrical panels / control boxes are installed
Fire and alarm systems and equipment and signage are installed (including Sprinkler system).