“I am not sure what you mean by “experimenting” but if you want to use the machine for production, you have
to take over the machine by signing the take-over-certificate.
Haarslev has already fulfilled the requirements as per contract 4000505-141016 and the machine is running well.
“If you insist on running a maximum capacity test, then you must provide the necessary conditions to do so.
That means both fish meal plants running maximum capacity and generating maximum amount of vapor.
Alternatively we can use live steam to top up the vapor and simulate maximum performance.
Only then can we measure the amount of condensate from vapor and compare to condensate from evaporator.
This test must be carried out before you can use the evaporator for regular production.”