Section 1-Vills 7,8 and 9-4 months from the Commencement Date.
Section 2-Villas 10, 11 and 12-7 mouths from the Project Manager’s instruction to commence works which shall be issued when the sub-structure drawings have been issued. The Contractor is required to have a minimum of 20 workers per villa under construction at any one time, the failure to maintain this level of labour will be considered breach of contract and this a failure of the Contractor to perform his obligations under the contract.