There are feedback from management meeting to our engineering
1. Filling valve leakage issue and NCR. This issue need action plan to change diaphragm as maintenance plan. - > Ratchaphum and Nuttapol will be leader
2. Top load of capping head including spike problem – QC and Production request spring as a spare part. Al so chuck spare part kit readiness. Ratchaphum and Nuttapol will be leader
3. Front / back pad of labeler including infeed screw. – Right now , Pad seem like to worn out again so. They ask for spare part ready to change. -- > Vissawa and Theerapat.
4. Seal ring at Syrup (B1.A1) often damaged. – They would like to see maintenance plan and why is often broken , have doubt on seal material and maintenance team have maintenance plan or not? -- >Thaned Aekkapon
5. Start DOR meeting next Monday 17 October, This meeting will held every day start from next week 9:30-10:00 at pepsi room . Supervisor on day shift have to joined.
Above need action plan with of maintenance plan and spare part. Please feedback on to me within Monday 17 October.