Following yesterday’s phone discussion with K'Prasert about process of send and receive PO's CPIM included with "Delivery Date confirmed" for part stamping and Aluminium (CNC) for meet to the our target with ISO. (KPI)
1. PO (Stamping&Alu.) : CPIM must send PO directly to K'Do. (CC ; K'Praset, K'Mattana and K'Sajeerat) and then K'Do will make a "Delivery Date confirmed" to CPIM.
2. K'Do will send E-Mail to CPIM, when KBK have problem in production process and it effect to delivery date.
3. Every information between CPIM and KBK we will communicating with telephone or meeting, but we will send e-mail for preventive for mistaken and we will have a evidence for confirm.
So K'Prasert has assigned to K'Do (K'Khampan) for responsible this process. But CPIM can contact directly with K'Mattana (Supervisor CNC) in only urgent case for plan Aluminium (CNC) and then inform to every department that are concern.
And for my e-mail as below I'm still waiting your reply for "Delivery date confirmed". Please reply asap. We would like to prepare our production Plan.