Dear P’A,
Noted with many thanks ka.
Is there any other supplier ? or any possibility to get earlier ka? i.e. choose item from their ATP or something like that?
Dear Muk,
This timeline refer from Ocean’s Jug. If your all requirements same as this project such as Request more sample ( 60 Pcs ), improve supplier on OGC quality standard, Request inspection at Supplier site. In experience, Time Should be 5 month krub.
Activity Impact for take time.
• Request more sample ( 60 Pcs ) ---- > Supplier ask payment & Accounting need time to do. If small lot sample ( 1-5 Pcs ), Free of Charge, No need accounting time.
• improve supplier on OGC quality standard ----- > Supplier need start new production because product in stock always not meet OGC standard, Take process for QA recommendation.
• Request inspection at Supplier site ---- > Travelling & Double inspection process.
Thank you