8. Report of review results, and postprocessing
8.1 Preparation and distribution of "Control System and Software Review Implementation Report"
(1) After the reviews of each stage, the meeting organizer shall promptly summarize the
results by using Form A and B of Control System and Software Review Implementation Report
(hereafter called "Review Report") by using Form A and B
(2) The meeting organizer shall distribute the Review Report to the related groups.
(3) Form A shall be used as cover sheet for the Review Report if a the copy of an electronic whiteboard is
used as Review Report.
(4) The review result shall be judged as:
(a) Acceptable: - No pointed out matter was adopted.
- A pointed out matter was "adopted", but the content can be
improved by a design change until the time of shipment of the
reviewed product.
(b) Unacceptable: Fundamental re-examination is required because of a defect in the
basic idea or basic structure of the design.
(c) Conditionally acceptable: The content of a pointed out matter that was "adopted", can be
improved by a design change until the time of design arrangement
for mass production.