• Once fracturing has been completed a period of upto 8 weeks is typically taken to test and monitor the well. Plugs are inserted and gas levels are monitored, both for production levels but also for health and safety reasons. Once the main period of testing has been completed the plugs can be drilled out to allow the gas to flow up the well bore. A permanent well head is then installed and the test well is closed until production commences