The forward pass is complete when at node n has been computed. By definition represents the longest path (duration) to node j
Backward Pass (Lasted Occurrence Times, ). Following the completion of the forward pass, the backward pass computations start at node j
Initial Step. Set to indicate that the earliest and latest occurrences of the
last node of the project are the same.
General Step j. Given that nodes p, q,…, and v are linked directly to node j by
outgoing activities (j,p), (j,q),…,and (j,v) and that the latest occurrence times of nodes p, q,…, and v have already been computed, the latest occurrence time of node j is computed as
The backward pass is complete when at node 1 is computed. At this point,
Base on the preceding calculations, an activity ( i, j) will be critical if it satisfies three conditions.
1.
2.
3.
The three conditions state that the earliest and latest occurrence time of end nodes i and j are equal and the duration fits “tightly” in the specified time span. An activity that does not satisfy all three conditions is thus noncritical.
By definition, the critical activities of a network must constitute an uninterrupted path that spans the entire network from start to finish.
Example 6.5-2
Determine the critical path for the project network in Figure 6.42. All the durations are in days.
The forward pass is complete when at node n has been computed. By definition represents the longest path (duration) to node jBackward Pass (Lasted Occurrence Times, ). Following the completion of the forward pass, the backward pass computations start at node jInitial Step. Set to indicate that the earliest and latest occurrences of the last node of the project are the same.General Step j. Given that nodes p, q,…, and v are linked directly to node j by outgoing activities (j,p), (j,q),…,and (j,v) and that the latest occurrence times of nodes p, q,…, and v have already been computed, the latest occurrence time of node j is computed as The backward pass is complete when at node 1 is computed. At this point, Base on the preceding calculations, an activity ( i, j) will be critical if it satisfies three conditions.1. 2. 3. The three conditions state that the earliest and latest occurrence time of end nodes i and j are equal and the duration fits “tightly” in the specified time span. An activity that does not satisfy all three conditions is thus noncritical. By definition, the critical activities of a network must constitute an uninterrupted path that spans the entire network from start to finish.Example 6.5-2Determine the critical path for the project network in Figure 6.42. All the durations are in days.
การแปล กรุณารอสักครู่..

The forward pass is complete when at node n has been computed. By definition represents the longest path (duration) to node j
Backward Pass (Lasted Occurrence Times, ). Following the completion of the forward pass, the backward pass computations start at node j
Initial Step. Set to indicate that the earliest and latest occurrences of the
last node of the project are the same.
General Step j. Given that nodes p, q,…, and v are linked directly to node j by
outgoing activities (j,p), (j,q),…,and (j,v) and that the latest occurrence times of nodes p, q,…, and v have already been computed, the latest occurrence time of node j is computed as
The backward pass is complete when at node 1 is computed. At this point,
Base on the preceding calculations, an activity ( i, j) will be critical if it satisfies three conditions.
1.
2.
3.
The three conditions state that the earliest and latest occurrence time of end nodes i and j are equal and the duration fits “tightly” in the specified time span. An activity that does not satisfy all three conditions is thus noncritical.
By definition, the critical activities of a network must constitute an uninterrupted path that spans the entire network from start to finish.
Example 6.5-2
Determine the critical path for the project network in Figure 6.42. All the durations are in days.
การแปล กรุณารอสักครู่..

ผ่านไปข้างหน้าจะสมบูรณ์เมื่อโหนด n ได้รับการคํานวณ โดยนิยามหมายถึงเส้นทางที่ยาวที่สุด ( เวลา ) โหนด J
ถอยหลังผ่านไป ( เวลาการเกิดครั้ง ) ต่อไปนี้ความสำเร็จของผ่านไปข้างหน้า การคำนวณถอยหลังผ่านไปเริ่มต้นที่โหนด J
เริ่มต้นขั้นตอน ชุด เพื่อบ่งบอกว่าเก่าที่สุด และเหตุการณ์ล่าสุดของ
ปมสุดท้ายของโครงการเหมือนกัน
ขั้นตอนทั่วไป Jให้ที่จุด P , Q , V . . . . . . . และจะเชื่อมโยงโดยตรงกับโหนด J โดย
กิจกรรมขาออก ( J , p ) j , Q ) , . . . , ( J , V ) และการเกิดครั้งล่าสุดของจุด P , Q , . . . , และ V ได้ถูกคำนวณใหม่ล่าสุด การเกิดของโหนด J จะคำนวณเป็น
ถอยหลังผ่านไปเรียบร้อย เมื่อโหนด 1 คํานวณ ณจุดนี้
ฐานในการคำนวณก่อนหน้านี้ได้มีกิจกรรม ( ฉันJ ) จะสำคัญถ้ามัน satisfies เงื่อนไขสาม .
1
2 .
3
สามสถานะที่เก่าที่สุด และเวลาที่เกิดขึ้นล่าสุดของโหนด I และ J จบเท่ากัน และระยะเวลาที่เหมาะกับ " แน่น " ในช่วงเวลาที่ระบุ . เป็นกิจกรรมที่ไม่ตอบสนองทั้ง 3 ข้อ จึง noncritical .
นิยามกิจกรรมที่สำคัญของเครือข่ายจะต้องเป็นปราศจากเส้นทางที่ครอบคลุมเครือข่ายทั้งหมดตั้งแต่ต้นจนจบ
ตัวอย่าง 6.5-2
หาวิถีวิกฤตสำหรับโครงการเครือข่ายในรูป 6.42 . เวลาทั้งหมดอยู่ในวัน
.
การแปล กรุณารอสักครู่..