weight that cannot be ignored. The DDG51 suffered from
severe operational issues due to the use of a solely weight
based cost estimate method. Designers believed that
decreasing the beam by 2ft would decrease costs. The
construction difficulty factor however, increased to such a
level that the overall cost of the ship increased. Also
operational issues arose due to the change since stretchers
couldn't fit in the 2ft narrower corridors