TOTAL PROJECT TIMING
Implement Assessment
Assignment Implementation Team / QMR
Do Implementation Plan
IMPLEMENTATION TEAM TRAINING
Day 1 : Intro & Implementation of ISO / TS 16949
Review Process & Document planning
Document Planning
Developing Flowchart
Project Review # 1
Developing Quality Document System
Quality Manual
Procedure Manual
Work Instruction
Form & Support Doc.
ISO / TS 16949 Suplement Training
APQP TEAM & Control Plan
MSA & PPAP
SPC
FMEA
Developing APQP TEAM / Control Plan / FMEA / SPC / MSA / PPAP
Project Review # 2
Register Selection
IMPLEMENTATION & OPERATE SYSTEM
Internal Audit Training
Internal Audit Program
Corrective Action & Improvement
Management Review # 1
Pre - Assessment by Consulation and QMR
Corective Pre - Assessment Note
Project Review # 3
Final Assessment dy 3 rd Party