PROJECT CERTIFICATION PHASE II
Upon completion of Phase I, the design phase of the project commences, known as Phase II of Project Certifi cation. In this phase,
detailed calculations of the loads on the turbine and its support structure must be carried out based on local environmental conditions.
In this case the turbine manufacturer Multibrid GmbH supplied the respective load calculations; these are used to design the fi nal
turbine support structure and to verify whether the resulting loads incurred by the turbine are within the design limits defi ned in
the wind turbine type certifi cate. The offshore sub-station, including the electrical installations, is also part of the Phase II design
verifi cation. In order to verify structural integrity, SGS performs parallel calculations for both the loads and structural design. Moreover,
submarine cables, met mast, logistics and decommissioning concept are also covered under this verifi cation.
Phase II culminates with the 3rd release by the BSH, which is essentially the starting signal for the applicant to commence installation
PROJECT CERTIFICATION PHASE IIUpon completion of Phase I, the design phase of the project commences, known as Phase II of Project Certifi cation. In this phase,detailed calculations of the loads on the turbine and its support structure must be carried out based on local environmental conditions.In this case the turbine manufacturer Multibrid GmbH supplied the respective load calculations; these are used to design the fi nalturbine support structure and to verify whether the resulting loads incurred by the turbine are within the design limits defi ned inthe wind turbine type certifi cate. The offshore sub-station, including the electrical installations, is also part of the Phase II designverifi cation. In order to verify structural integrity, SGS performs parallel calculations for both the loads and structural design. Moreover,submarine cables, met mast, logistics and decommissioning concept are also covered under this verifi cation.Phase II culminates with the 3rd release by the BSH, which is essentially the starting signal for the applicant to commence installation