Dear Paradee/Laila,
For the 2 OAs (PK parts and PEC parts) which you had requested to ship together with Epsilon crane, this will pose a problem.
Since the container will be shipped out next week, approx. 19 Nov, PK parts should be ready, but PEC parts (9units of BKA41) requires 3 weeks lead time. Very likely, the PEC parts cannot catch the container shipment.
Does Chainant has any other container shipment that can match this PEC part delivery date? If not, I will need your advice on your preferred shipment for PEC parts.