Please note that, We will delivery all cooling coil for novolux-1 on October 27, 2014
And we will start to installation of cooling coil for AHU-A on November 1&2,2014
1.On November 1, 2014 – from 15.00 – 24 hrs.
2.On November 2, 2014 – from 08.00 – 24 hrs.
I will send you the name of people asap