2) Ground Stability.• When planning a lift consideration must be given การแปล - 2) Ground Stability.• When planning a lift consideration must be given ไทย วิธีการพูด

2) Ground Stability.• When planning

2) Ground Stability.
• When planning a lift consideration must be given to the ground conditions. Outrigger and track loading should be established before sitting the crane, the safe load limits should be identified against the specification of the concrete, foundations etc. of the area involved. For other areas the density and compaction qualities should be assessed.
• Underground hazards arise from cellars and basements (filled or not), recently backfilled excavations, tidal or flood water areas where the ground water table is high, buried pipes and mains etc.
• On soft ground it will be necessary to pack solid material(timber, digger mats, hard core) beneath crawlers and/or outriggers to allow for setting under load. Bearing plates or grillage may be necessary to distribute the loads. For lorry mounted and mobile cranes, if there is any doubt about the suitability of the ground, the following procedure must be adopted:
- Test by lifting the load approximately 150 mm. and holding for a period over one outrigger at maximum possible safe radius to see if the outrigger sinks.





0/5000
จาก: -
เป็น: -
ผลลัพธ์ (ไทย) 1: [สำเนา]
คัดลอก!
2) Ground Stability.
• When planning a lift consideration must be given to the ground conditions. Outrigger and track loading should be established before sitting the crane, the safe load limits should be identified against the specification of the concrete, foundations etc. of the area involved. For other areas the density and compaction qualities should be assessed.
• Underground hazards arise from cellars and basements (filled or not), recently backfilled excavations, tidal or flood water areas where the ground water table is high, buried pipes and mains etc.
• On soft ground it will be necessary to pack solid material(timber, digger mats, hard core) beneath crawlers and/or outriggers to allow for setting under load. Bearing plates or grillage may be necessary to distribute the loads. For lorry mounted and mobile cranes, if there is any doubt about the suitability of the ground, the following procedure must be adopted:
- Test by lifting the load approximately 150 mm. and holding for a period over one outrigger at maximum possible safe radius to see if the outrigger sinks.





การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 2:[สำเนา]
คัดลอก!
2) Ground Stability.
• When planning a lift consideration must be given to the ground conditions. Outrigger and track loading should be established before sitting the crane, the safe load limits should be identified against the specification of the concrete, foundations etc. of the area involved. For other areas the density and compaction qualities should be assessed.
• Underground hazards arise from cellars and basements (filled or not), recently backfilled excavations, tidal or flood water areas where the ground water table is high, buried pipes and mains etc.
• On soft ground it will be necessary to pack solid material(timber, digger mats, hard core) beneath crawlers and/or outriggers to allow for setting under load. Bearing plates or grillage may be necessary to distribute the loads. For lorry mounted and mobile cranes, if there is any doubt about the suitability of the ground, the following procedure must be adopted:
- Test by lifting the load approximately 150 mm. and holding for a period over one outrigger at maximum possible safe radius to see if the outrigger sinks.





การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 3:[สำเนา]
คัดลอก!
2 ) เสถียรภาพของดิน .
- เมื่อวางแผนยกการพิจารณาจะต้องให้สภาพดิน Outrigger และติดตามโหลดน่าจะตั้งขึ้นก่อนนั่งเครน จำกัด โหลด เซฟ ควรจะระบุต่อคุณสมบัติของคอนกรีต มูลนิธิ ฯลฯ ของพื้นที่ที่เกี่ยวข้อง สำหรับพื้นที่อื่นๆ ความหนาแน่นและคุณภาพการบดอัด ควรประเมิน
- อันตรายที่เกิดขึ้นจากใต้ดินและห้องใต้ดินชั้นใต้ดิน ( เต็มหรือไม่ ) เมื่อเร็ว ๆนี้ backfilled ขุดค้นน้ำขึ้นน้ำลงหรือท่วมพื้นที่น้ำที่มีน้ำพื้นโต๊ะสูง ฝังท่อและท่อฯลฯ
- บนดินอ่อน จะต้องแพ็คแข็งวัสดุ ( ไม้ , เสื่อ , ขุดฮาร์ดคอร์ ) ภายใต้โปรแกรมตรวจสอบและ / หรือ outriggers เพื่อให้สำหรับการตั้งค่าภายใต้โหลดแบริ่งหรือ grillage แผ่นอาจจะต้องมีการกระจายโหลด สำหรับรถบรรทุกติดเครน และโทรศัพท์มือถือ หากมีข้อสงสัยใด ๆเกี่ยวกับความเหมาะสมของดิน ขั้นตอนต่อไปนี้จะต้องประกาศใช้ :
- ทดสอบประมาณ 150 มม. ยกโหลด และถือเป็นระยะเวลากว่าหนึ่ง Outrigger ที่เป็นไปได้สูงสุดที่ปลอดภัยรัศมีเพื่อดูว่า





เรือกันจม
การแปล กรุณารอสักครู่..
 
ภาษาอื่น ๆ
การสนับสนุนเครื่องมือแปลภาษา: กรีก, กันนาดา, กาลิเชียน, คลิงออน, คอร์สิกา, คาซัค, คาตาลัน, คินยารวันดา, คีร์กิซ, คุชราต, จอร์เจีย, จีน, จีนดั้งเดิม, ชวา, ชิเชวา, ซามัว, ซีบัวโน, ซุนดา, ซูลู, ญี่ปุ่น, ดัตช์, ตรวจหาภาษา, ตุรกี, ทมิฬ, ทาจิก, ทาทาร์, นอร์เวย์, บอสเนีย, บัลแกเรีย, บาสก์, ปัญจาป, ฝรั่งเศส, พาชตู, ฟริเชียน, ฟินแลนด์, ฟิลิปปินส์, ภาษาอินโดนีเซี, มองโกเลีย, มัลทีส, มาซีโดเนีย, มาราฐี, มาลากาซี, มาลายาลัม, มาเลย์, ม้ง, ยิดดิช, ยูเครน, รัสเซีย, ละติน, ลักเซมเบิร์ก, ลัตเวีย, ลาว, ลิทัวเนีย, สวาฮิลี, สวีเดน, สิงหล, สินธี, สเปน, สโลวัก, สโลวีเนีย, อังกฤษ, อัมฮาริก, อาร์เซอร์ไบจัน, อาร์เมเนีย, อาหรับ, อิกโบ, อิตาลี, อุยกูร์, อุสเบกิสถาน, อูรดู, ฮังการี, ฮัวซา, ฮาวาย, ฮินดี, ฮีบรู, เกลิกสกอต, เกาหลี, เขมร, เคิร์ด, เช็ก, เซอร์เบียน, เซโซโท, เดนมาร์ก, เตลูกู, เติร์กเมน, เนปาล, เบงกอล, เบลารุส, เปอร์เซีย, เมารี, เมียนมา (พม่า), เยอรมัน, เวลส์, เวียดนาม, เอสเปอแรนโต, เอสโทเนีย, เฮติครีโอล, แอฟริกา, แอลเบเนีย, โคซา, โครเอเชีย, โชนา, โซมาลี, โปรตุเกส, โปแลนด์, โยรูบา, โรมาเนีย, โอเดีย (โอริยา), ไทย, ไอซ์แลนด์, ไอร์แลนด์, การแปลภาษา.

Copyright ©2025 I Love Translation. All reserved.

E-mail: