The programming project of image processing using a newly devised algorithm is
outsourced to an external vendor. In order to ensure the strict control of handling
information, which of the following is an item that must be included in the contract?
a) Maintenance plan after development
b) Organizational structure of development
c) Performance assurance of the program
d) Protection of confidentiality