Quite commonly, cost planning is observed to be an iterative process wherein project planner update
the cost of project based on information updates available with him/her. As you would have seen, in
initial phase, the ROM estimates are within a broad range of ±50% of the proposed estimate and as
project progresses, the estimate may get updated to the tune of ±20% or less.