Total number of story points planned for this release
Total number of planned development weeks
Total budget for the release
Number of development weeks elapsed to date
Number of story points completed to date
AW/PW
CSP/PSP
Total budget spent to date
Budgeted cost of the story points that were scheduled to be completed as of today: PPC * BAC
Budgeted cost for the story points actually completed as of today APC* BAC
Difference between planned budget and actual spend EV-AC
Difference between planned schedule and actual time spent: EV - PV
EV/AC
EV/PV
Based on current state, how much additional budget is needed to complete the release: 1/CPI * (BAC - EV)
Based on current state, what the total estimated cost of the release will be at completion EAC = AC + ETC
Based on the current state the total estimated time needed to complete the release 1/SPI*PW