1.7.13 PARTIAL POSSESSION / SECTIONAL COMPLETION
The Contractor is expected to use rope access methods to complete the works. The works can therefore be divided into vertical ‘drop zones’. The works sequence is expected to be from top to bottom of the building. Any sectional completion or handover agreed with the Client will be on the basis of fully completed drops, and not partially completed drop zones. This is because access to lower zones must pass through completed works and there is some risk of damage to completed works.